Cycle time: 30s
Floor area: 2300*850 cm
Main workstation introduction:
Large Ring Gear Installation & UVW O-ring Inspection
Idler Gear Bushing Press-fit
Planetary Gear Bushing Press-fit
Planetary Gear & Sun Gear Installation
Solenoid Valve Installation
MGU Middle Housing Pre-assembly and Fastening
Run-in & Transmission Function Test, Air Tightness Test
Terminal Resistance Welding, Product Cleaning
PCBA Programming & Shunt Calibration & Installation
Selective Wave Soldering
AOI & Manual Solder Ball Brushing, Re-inspection
Calibration & MGU Function Test
MGU Cover Installation, Offline Stationary Resting
MGU Air Tightness Test